ABSTRACT

Tsunami - Emergency Tsunami Reconstruction Project (ETRP) assisted by World Bank - Tamil Nadu Slum Clearance Board - Construction of tenements for Tsunami hit slum families in Chennai and Tiruvallur Districts - Tsunami Planning Co-ordination and Monitoring Cell and three Divisions - Increment Operating Cost - Release - Orders - Issued.

 

 Revenue (NC.IV.1) Department

 
G.O. Ms. No.92    Dated:  06-03-2009
     Read :
  1. G.O. Ms. No.271, Revenue (NC.IV.1) Department, Dated:24.5.2007.
  2. G.O. Ms. No.431, Revenue (NC.IV.1) Department, Dated:10.7.2008.
  3. From the Managing Director, Tamil Nadu Slum Clearance Board Lr. No. M1/20265/08, Dated:7.11.2008 and 20.1.2009.

 

ORDER:-

In the G.O. first read above, the Government have sanctioned the formation of Tsunami Planning Co-ordination and Monitoring Cell and three Divisions in Tamil Nadu Slum Clearance Board for a period of two years.

2. In the G.O. second read above, the Government have sanctioned the further continuation of Tsunami Planning Co-ordination and Monitoring Cell and three Divisions in Tamil Nadu Slum Clearance Board upto 31.3.2009.

3. In the letter third read above, the Managing Director, Tamil Nadu Slum Clearance Board has requested to release funds for the Project Implementation Unit of Emergency Tsunami Reconstruction Project (ETRP) for the staff and administrative expenses component of Tsunami Planning Co-ordination and Monitoring Cell and three divisions for Emergency Tsunami Reconstruction Project (ETRP) for the year 2008-2009. He has also stated that the Government have provided a budgetary support of Rs.100.00 lakhs in the RE 2008-2009.

4. The Government after careful examination, accept the request of the Managing Director, Tamil Nadu Slum Clearance Board and accord sanction for a sum of Rs.1,00,00,000/- (Rupees one crore only) for the Incremental Operating Cost under Emergency Tsunami Reconstruction Project (ETRP) towards the staff cost and administrative expenses of the Tsunami Planning Co-ordination and Monitoring Cell and three divisions of the Emergency Tsunami Reconstruction Project (ETRP) for the year 2008-2009 as mentioned in the Annexure to this order.

5. The expenditure sanctioned in paragraph 4 above shall be debited to the following head of account:-

"2216 - Housing-02 Urban Housing-190 Assistance to Public sector and other undertakings - Schemes in the Eleventh Five Year Plan-II. State Plan-QA. World Bank assisted scheme under Emergency Tsunami Reconstruction Project (ETRP) - Project Implementation Unit - Tamil Nadu Slum Clearance Board-09 Grants-in-Aid-03 Grants for Specific Schemes."

(DPC 2216-02-190-QA-0909)

6. The amount sanctioned in paragraph 4 above shall not be paid in cash but credited to the following head of account:-

"K. Deposits and Advances (b) Deposits not bearing interest 8443-00 Civil Deposits-800 Other Deposits CA Deposits of Tamil Nadu Slum Clearance Board."

(DPC 8443-00-800-CA-000J)

7. Necessary provision will be made in the RE/FMA 2008-2009. Pending provision of funds in RE/FMA 2008-2009, the Director of Treasuries and Accounts, Chennai, is authorised to draw the amount sanctioned in paragraph 4 above by means of an account payee cheque in favour of Personal Deposit account of Tamil Nadu Slum Clearance Board by indicating the Account number there on and disburse the same to the Tamil Nadu Slum Clearance Board.

8. The Managing Director, Tamil Nadu Slum Clearance Board is requested to send the Statement of Expenditure, Utilization Certificate and the Progress reports in consultation with the Project Director (ETRP/TEAP) to the Government/ Accountant General.

9. This order issues with the concurrence of Finance Department, vide its U.O. No.8827/Housing/09, Dated:5.7.2009.

(By Order of the Governor)

 

K. DEENABANDU,

PRINCIPAL SECRETARY TO GOVERNMENT.

To

The Principal Secretary/ Commissioner of Revenue Administration, Chepauk, Chennai-5.

The Officer on Special Duty (Relief and Rehabilitation) and Project Director (ETRP & TEAP) (i/c), Chepauk, Chennai–5.

The Managing Director, Tamil Nadu Slum Clearance Board, Chennai-5.

The Secretary, Department of Economic Affairs (ADB), Ministry of Finance, Government of India, New Delhi.

The Country Director, India Resident Mission, ADB, No.4, San Martin Marg, Chanakyapuri, New Delhi.

The Task Team Lead, ETRP, World Bank, 70, Lodhi Estate, New Delhi 110 003.

The Secretary to Government, Housing and Urban Development Department, Chennai-9.

The Director of Treasuries & Accounts, Chennai-15.

The Accountant General, Chennai-18.

The Pay and Accounts Officer (South), Chennai-35.

Copy to:-

The Finance (Housing/ BG.II) Department, Chennai–9.

Sf/ Sc.

 

/Forwarded/By Order/

SECTION OFFICER.

Revenue (NC.IV.1) Department

 

(G.O. Ms. No.92, Revenue Department, Dated: 6.3.2009)

Annexure

 

Emergency Tsunami Reconstruction Project - Incremental Operating Cost for Tsunami Planning Co-ordination and Monitoring Cell and its Divisions.

 

Sl. No. Designation Total Nos. Scale of Pay Cost per annum (Rs. in Lakhs)
TECHNICAL
TSUNAMI CELL
1 Superintending Engineer (Monitoring) 1 14300-400-18300 2.93
2 Executive Engineer 1 10000-325-15200 2.27
3 Assistant Executive Engineer 1 8000-275-13500 1.94
4 Planning Officer 1 8000-275-13500 1.94
5 Assistant Planner 1 8000-275-13500 1.935
6 Assistant Engineer 3 6500-200-10500 4.59
DIVISIONS & PROJECT CIRCLE
7 Executive Engineer (Projects) 3 10000-325-15200 6.80
8 Assistant Executive Engineer (Projects) 8 8000-275-13500 15.48
9 Community Development Officer 1 8000-275-13500 1.94
10 Assistant Engineer (Projects) 16 6500-200-10500 24.48
11 Draughts Man G.II 3 5500-175-9000 3.915
12 Supervisor 16 3000 (Consolidated) 5.76
NON TECHNICAL
TSUNAMI CELL
1 DRO/ Project Coordinator 1 25000 (Consolidated) 3.00
2 Steno Typist 1 5000-150-8000 1.17
3 Typist 1 3200-85-4900 0.73
4 Assistant Account Officer 1 6500-200-10500 1.53
5 Manager 1 15000 (Consolidated) 1.80
6 Assistant 2 4000-100-6000 1.80
7 Office Assistant 2 2550-85-2660 0.94
8 Data Entry Operator 3 7500 (Consolidated) 2.70
DIVISION
9 Superintendent (Division) 3 6500-200-10500 4.59
10 Assistant (Division) 3 4000-100-6000 2.70
11 Office Assistant (SE Office) 2 2550-85-2660 0.94
12 Office Assistant (Division) 3 2550-85-2660 1.41
13 Computer Assistant (Division) 3 7000 (Consolidated) 2.52
TOTAL 99.79
Other expenditures 0.21
TOTAL 100.00

 

K.DEENABANDU,

PRINCIPAL SECRETARY TO GOVERNMENT.

 

/True Copy/