Organisation
Activities Performance
Anna Silk Exchange TANSILK
Sericulture Development Main
Page |
||
|
|
||
Financial Performance
The financial outlay and Expenditure upto March 2002 under Plan and Non-Plan schemes are indicated below.
(Rs. in lakhs)
|
S. No. |
Name of the Scheme |
Budget Estimate for 2001-02 |
Revised Estimate for 2001-02 |
Actual Expenditure upto MARCH-2002 |
|
1 |
Plan Schemes Part - I Part - II |
70.000 20.940 |
54.000 19.860 |
0.954 19.800 |
|
2 |
Non- Plan |
2160.480 |
1990.850 |
1950.824 |
|
3 |
Hill Area Development Programme |
8.010 |
8.000 |
4.630 |
|
4 |
Western Ghat Development Programme |
23.110 |
16.830 |
16.718
|
|
5 |
Schemes Financed by autonomous bodies |
2.280 |
3.930 |
1.351 |
|
6 |
SERI – 2000 |
118.340 |
32.790 |
- |
|
Total |
2403.160 |
2126.260 |
1994.227 |
Technical Service Centers
Technical Service Centers are the front line units and they motivate the farmers to take up mulberry cultivation and silkworm rearing. Technical guidance for mulberry plantation, garden maintenance, disease and pest control, silkworm rearing, prevention of diseases, marketing of cocoon, etc., are being provided to the farmers. The details of Technical Service Centers are furnished separately.
The produce of the sericulturists, i.e., cocoon is sold to the silk reelers in cocoon markets after quality assessment, through open bidding system, to fetch reasonable price on the spot.
The Districtwise Mulberry area, Layings consumption, Cocoon production, and Raw- Silk production details for the past five years are furnished separately.