ABSTRACT

Tsunami - Relief and Rehabilitation – World Bank aided Emergency Tsunami Reconstruction Project (ETRP) - Documentation of relief and rehabilitation activities in Cuddalore District - Expenditure incurred - Rs.44,700 - Sanctioned – Orders - Issued.


Revenue NC IV (1) Department

G.O.Ms.No.522
Dated: 11.8.2006.

Read:

1. G.O.Ms.No.384, Revenue, Dated 01.07.2005

2. G.O.Ms.No.418, Rev (NC III) Dated 20.07.2005

3. Agenda for Empowered Committee meeting dated 11.07.2006

4. Officer on Special Duty (RR) and Project Director (ETRP and TEAP) D.O. TRR-EAP1/52820/2006, Dated: 21.7.2006.

****

ORDER:

In the G.O. first read above, Government have issued orders according administrative sanction for the implementation of the Emergency Tsunami Reconstruction Project (ETRP) with World Bank Assistance at a cost of Rs.1852.74 crore for housing reconstruction, restoration of livelihood, repairs / reconstruction of public buildings, providing Technical assistance and training and implementation support for tsunami affected victims.

2. In the G.O. Second read above, the Government have constituted an Empowered Committee to clear the projects to be implemented with the World Bank assistance sanctioned in G.O. first read above.

3. The Collector of Cuddalore District has submitted proposal for sanction of funds for of Rs.44,700/- for printing and publication of the book entitled "Tsunami and One Year After" about Cuddalore district.

4. The Project Director (ETRP & TEAP) placed the above proposal before the Empowered Committee meeting held on 11.07.06. The Empowered Committee has approved the above proposal.

5. The Government, after careful consideration, accept the decision of the Empowered Committee and accord sanction of Rs.44,700 (Forty four thousand seven hundred only) for printing and publication of the book entitled "Tsunami and one year After" about Cuddalore District.

6. The Expenditure sanctioned in paragraph 5 above shall be debited to the following Head of Account

"2070 00 – Other Administration Services – 800 - Other Expenditure - II.State Plan – QA World Bank assisted Scheme under Emergency Tsunami Reconstruction Project (ETRP) - Project Management Unit - Revenue Administration - 71. Printing charges "

(DPC 2070 00 800 QA 7101)

7. Necessary funds will be provided in RE/FMA 2006-07.

8. Pending provision of such funds, the Special Commissioner and Commissioner of Revenue Administration is authorised to draw and disburse the amount sanctioned in paragraph 5 above to Collector, Cuddalore. The Special Commissioner and Commissioner of Revenue Administration has requested to include this expenditure while sending RE/FMA proposed for 2006-07.

9. This order issues with the concurrence of Finance Department vide its U.O.No.46088/Revenue/2006-1, dated 10.8.2006 and ASL No.380.

(BY ORDER OF THE GOVERNOR)

S. AUDISESHIAH,

SECRETARY TO GOVERNMENT.

To

The Special Commissioner & Commissioner of Revenue Administration, Chennai-5

The O.S.D. & Project Director (ETRP & TEAP), Chennai-5

The Secretary, Department of Economic Affairs (FB) Ministry of Finance Government of India, New Delhi

The Task Team Leader, ETRP, World Bank, No.70, Lodhi Estate, New Delhi -3.

The District Collector Cuddalore

The Special Commissioner of Treasuries and Accounts, Chennai-15

The Pay and Accounts Officer (East), Chennai - 5

The Treasury Officer, Cuddalore District.

The Accountant General, Chennai-18

Copy to

The Finance (Rev/RD/BG-I/BG-II/B Co-ord / EAP) Department, Chennai-9

Rural Development Department, Chennai-9

/Forwarded by order/