GOVERNMENT
OF TAMIL NADU
ABSTRACT
Tourism
Promotion of Tourism Government of India Assisted Scheme 2005
2006 Development of Adi Sankara Tourist Circuit in Tamil Nadu at a cost
of Rs.443 lakhs Administrative approval - first instalmet of Rs.354.40 lakhs
released by Government of India - Sanctioned Orders Issued.
Information
& Tourism (T.1) Department
G.O.Ms.No.3
Dated: 02-01-2006
Read:-
Commissioner
of Tourism, Chennai-2 D.O. Letter No. 1680/P&D-1/04 dt. 23.12.2004.
Govt.
Lr.No.194/T.1/2005 dt. 28.1.2005.
From
the Ministry of Tourism, Government of India, New Delhi Lr.No.5-PSW/97/04 dt.
3.5.2005.
From
the Commissioner of Tourism,Lr.No.1680/P&D-1 2004 dt.3.6.2005.
-----
ORDER:-
1.
A proposal at an estimated cost of Rs.450.70 lakhs for the development of the
places associated with the visit of Sri Adi Sankara was sent by the Commissioner
of Tourism to Government. The proposal was duly recommended by the Government
and forwarded to Ministry of Tourism, Government of India, New Delhi for
according sanction.
2.
The Ministry of Tourism, Government of India, has conveyed the
Sanction
of Rs.443.00 lakhs for the development of Sri Adi Sankara Tourist Circuit
covering Mangadu, Tirvotriyur, Chidambaram, Mayiladuthurai, Kumbakonam,
Tiruchirapalli, Tiruchendur and released a sum of Rs.354.40 lakhs being 80% of
the total cost of the projects. The Commissioner of Tourism stated that the
amount received from Government of India has been remitted into State Government
account.
3.
The Commissioner of Tourism has therefore requested the Government to approve
the Scheme for development of Adi Sankara Tourist Circuit at a cost of Rs.443
lakhs and to sanction the first instalment of Rs.354.40 lakhs (80%) released by
Government of India to the District Collectors concerned to commence the work.
4.
Government have carefully examined the proposal of Commissioner of
Tourism
and have decided to accept it. Accordingly the Government of India assisted
Scheme of development of Adi Sankara Tourist Circuit in Tamil Nadu covering
Mangadu,
Thiruvotriyur, Chidambaram, Myladuthurai, Kumbakonam, Tiruchirapalli and
Tiruchendur at a cost of Rs.443 lakhs is duly approved by Government. The
Components of the Scheme are detailed below:-
|
Scheme
Proposed
|
Amount
sanctioned by M.O.T., G.O.I. Rs. ( in Lakhs)
|
Amount
released(80%)by G.O.I. first instalment (to be released to the District
Collectors concerned
|
|
Mangadu
a)Providing Cement Concrete road at Shanmuganandha Swamy Koil Street. b)
Providing Cement Concrete road at Vaikunda Perumal Koil Street. c)
Providing Cement Concrete road at Valleeswaran Koil Street. k) Providing
Cement Concrete road at Othavadai Street. I) Providing Sodium Vapour
lamp. m) Landscaping the vacant site in between Sri Kamatchi Amman
Temple. n) Landscaping inside Sri. Valleeswaran Temple
|
10.00
10.00 21.40 10.45 1.35 4.65 8.00
|
|
|
Total
|
65.85
|
52.68
|
|
Thiruvotriyur:-
Basic amenities for tourists at Arulmigu Mahalakshana moorhy Temple,
Thiruvotriyur 1) Construction of toilet to both gents and ladies for
tourists. 2) External water supply and sanitary arrangements 3) External
Electrification 4) Provision for signage arrangement. 5) Erection of
bore well 6) Supply and erection of compressor motor, pipeline
Arrangements. 7) Construction of overhead tank 8) Construction of
Dormitory block to Pilgrims. 9) External water supply, sanitary
arrangements. 10) Petty Supervision and unforeseen items. 11) Providing
landscaping. 12) Providing chain line fencing. 13) Providing colour
paints, flower plants. 14) Construction of Kerb wall. 15) Providing
pathway. 16) Providing covering arrangements over pathway. 17) Providing
lighting arrangements. 18) Painting in kerb. II. Providing C C slab road
work at Sannathi street.
|
2.77
0.10 0.40 0.25 0.75 10.07 - 0.58 0.25 0.09 0.84 0.39 0.30 0.30 0.10 0.07
18.60
|
|
|
Total
|
35.54
|
28.43
|
|
Chidambaram
a)Platform on north side of South Car Street. b) Platform on south side
of South Car Street. c) Platform on east side of West Car Street. d)
Platform on west side of West Car Street. e) Development of Gandhi park.
f) Development of Govindasamy street park. g) Development of Manmadasamy
Nagar park. h) Development of Sabanayagar Street park. i) Platform to
Railway station Road. j) Platform to Venugopal Street. k) Landscaping at
Bus-stand. l) CC Road with platform in 4 car Sannathi Street. m)
Modernising East car street toilet. n) Thillaikali and Nataraja temple
connecting road. o) Lighting of Thillaikali and Nataraja temple road. p)
Renovation of bus-stand clock tower. q) Sign Board in 4 Car Street. r)
Protected drinking water supply at East Car Street.
|
24.00
18.00 26.00 22.00 5.00 3.00 3.50 3.00 13.00 27.00 3.00 19.00 12.00 6.00
4.00 1.00 2.00 1.00
|
|
|
Total
|
192.50
|
154.00
|
|
Mayiladuthurai
a) Providing lighting system around Mayurandavar temple
|
12.90
|
|
|
Total
|
12.90
|
10.32
|
|
Kumbakonam
-Arulmighu Kasiviswanathar Temple h) Construction of overhead tank and
landscaping at Sri Kasi viswa nathar temple at Kumbakonam. Arulmigu
Nageswarar Temple i)Construction of overhead tank, pump room, providing
pump room and pump connection j)Construction of toilet block, floor and
wall tiles and sundries and sanitary arrangements. k) Providing
landscaping arrangements around the Nandavanam. Arulmigu Adi
Kumbaeswaran Temple l) Construction of overhead tank, toilet block and
landscaping at Sri Adi Kumbeswarar temple at Kumbakonam. m) Construction
of toilet block, flood tiles and wall tiles, Sanitary arrangements and
sundries. n) Provision for landscaping arrangements. Arulmigu
Swaminathan Swamy Temple at Swamimalai i)Construction of dormitory type
accommodation. j)Provision for external water supply. k)Provision for
sanitary arrangements. l)Provision for external electrification.
m)Provision for furniture n) Provision for sundries. o) Construction of
over head tank p) Construction of toilet block
|
4.00
3.00 1.70 Except Sanitary arrange- -ment Rs.30,000) 3.00 3.00 1.70
Except Sanitary arrange- ment Rs.30,000) 10.00 12.64 - - - 0.50 0.51
3.00 4.40 (Except external Sanitary and electrifica - -tion works
(Rs.40,000+20,000)
|
|
|
Total
|
38.45
|
30.76
|
|
Tiruchirapalli
c)Providing of toilets and bathrooms of Arulmigu Agilandeswari Temple,
Thiruvanakoil d)Benching and pointing the rock steps up to Uchiplliyar
Koil at Rock Fort, Tiruchirapalli.
|
4.51
(Except- centage charge Rs.49,000) 1.00 (Except centage charge
Rs.10,000)
|
|
|
Total
|
5.51
|
4.41
|
|
Tiruchendur
a) Improvements of Pedestrain pathway. b) Improvements of roads
|
74.25
18.00
|
|
|
Total
|
92.25
|
73.80
|
|
Grand
Total
|
443.00
|
354.40
|
5.
Sanction is also accorded for a sum of Rs.354.40 lakhs (Rupees three hundred and
fifty four lakhs and forty thousand only) released by Government of India as
first instalment to the Collectors concerned for the implementation of this
Scheme subject to the usual following terms and conditions stipulated by
Government of India in Ministry of Tourism, Government of India sanction
No.5-PSW/97/2004, dated 3.5.2002.
6
The expenditure shall be debited to the following head of account:-
3452
Tourism 01 Tourist Infrastructure 101 Tourist centre SP construction of way
side facilities 09 Grants in Aid 01 grants for current expenditure
(DPC.No.3452 01 101 SP 0916)
7.
The Commissioner of Tourism is authorized to draw and disburse the amount
sanctioned in para 5 above and disburse it to the Collectors concerned to
commence the work.
8.
Necessary Funds will be provided in RE/FMA 2005-2006. The Commissioner of
Tourism is requested to send necessary proposal to Government, Finance
Department for the provision of funds in the Revised Estimate/FMA for 2005
2006 at the appropriate time without fail. The Commissioner of Tourism is also
requested to watch the progress of this work and send periodical report to
Government. The Commissioner of Tourism is further requested to get utilization
certificate from the concerned authorities and send it to Government of India
for the release of the balance amount.
The
Commissioner of Tourism is requested to fix time schedule for Execution of work
before disbursement to the executing agency.
This
order issues with the concurrence of Finance Department vide its U.O. No.
90833/I&T/05, dated 29.12.2005 and ASL.No.1312.
(By
Order of the Governor)
V.Varaprasada
Rao,
Secretary
to Government
To
The
Commissioner of Tourism, Chennai.2
The
Collectors concerned
The
Pay and Accounts Officer, Chennai-9
The
Pay and Accounts Officer, Chennai-9 thro
The
Commissioner of Tourism. Chennai-2
The
Accountant General, Chennai-9/18.
The
Secretary, Ministry of Tourism, Government of India, New Delhi
Copy
to:
O/o.
Chief Minister, Chennai-9
Special
PA to Minister (Tourism), Chennai-9
P.S.
to Secretary, I & T Dept., Chennai-9
Finance
(I&T)(BG.II) Department., Chennai-9
PD&SI
Department, Chennai.9
//
forwarded by order //
Section
Officer |